Site Recce

Published on Mar 19, 2016

No Description

PRESENTATION OUTLINE

Site Recce

Things to look out for!
Photo by andercismo

Information

  • Venue
  • Duration of setup
  • Event Duration
  • Tear Down Duration
  • Purpose and function
  • Capacity
  • Paper work
Photo by Calistobreeze

Taking Measurements

  • Trees
  • Awning
  • Leveling
  • Ground Conditions

Trees

  • Height & protrusion of roots
  • Height & protrusion of brunches
  • Will the branches and roots obstruct the marquee?

Awning

  • Height
  • Protrusion depth
  • Direction of gradient
  • Build over or under

Leveling

  • Highest point of tent base plate and wooden flooring
  • Difference between highest and lowest point
Photo by ArturoYee

Ground Conditions

  • Grass - Piling, Steel Plate
  • Concrete & Tarmac - Counter Weights
  • Tiles - Need protection
  • Sand - Stability
Photo by rvcroffi

Site consideration

  • Vehicle Accessibility
  • Loading and unloading
  • Equipment Accessability
  • Lighting
  • Electrical power source
  • Water Source
  • Lightning Protection
  • Ground Protection
Photo by Mr.Tea

Vehicle ACCESSIBILITY

  • Can lorry and lorry crane reach site?
  • Ground level or roof top?
  • Distance between unloading site to setup venue
  • Tools or equipments we can use to shift logistics
Photo by Ryan Holst

Loading & unloading

  • Space available to unload and load logistics
  • Equipments that are needed for loading & unloading

Equipment accessibility

  • If equipment such as mobile crane, boomlift & forklift is needed on site?
  • Ground condition suitable?
  • Can equipment reach deployment site? (Turning radius and working space

Lighting

  • Night Work required?
  • Setup venue light sufficient?
  • Need to bring in tower light?

Electrical Source

  • Electricity from venue or generators?
Photo by State Farm

Electrical from venue

  • Tapping power from 13amp 3 pin socket or electrical panel?
  • Size of the power tapping from panal?
  • Requires LEW single line endorsement?
  • Bonding & Earthing?

Electrical From Generators

  • Size of generator needed?
  • LEW or EMA Cert required?
  • Type of fencing and number of DB Box required?
  • Position and distance between generator & DB Box position?
  • Cable trays needed?
Photo by Tom Raftery

WAter Source

  • Water from venue or water tank if needed?
  • Discharge water direct or waste tank?
  • From venue - any application needed?
  • Pipe length and protection of pipe?

Lightning protection

  • Does venue owner or organiser needs it?
  • Is the set up on an open space with no tall buildings nearby?
  • Need to ask LEW for site visit for reccomendations and expertise
  • The highest point of our marquee?
Photo by gerlos

Ground protection

  • Understand loading of site & fire engine access
  • Prevention of rust stains on tiles (Old carpet or rubber mat)
Photo by uair01

Reccomendation

  • Understand your products
  • Check stock availability
  • Guttering issues
  • Simple layout
  • Flowing direction of rainwater

Guttering

  • Check if guttering can be tied to permanent structure
  • Length and height of guttering
  • The longer the canvas guttering the lower the gutter will go (Due to the need for gradient)
Photo by akeg

Before Leaving

  • Taking photos
  • Draw a simple sketch
  • Know the position of upright
Photo by clickykbd

Thank YOU

Photo by monkeyc.net